• BRIDGEWATER POINT •

• LATEST UPDATE •

DECEMBER 2018.


Block A

Now Complete.

Block B 

Completions to being Start of August.

Floors 1, 2,3, 4, 5, 6  are  complete.

Floors 7 are 95% complete with final decoration and testing and commissioning works being completed.

The external podium works has steelwork, metal deck and concrete poured,  Final brickwork to façade complete, waterproofing to deck progressing well with external blockwork commencing, surface finishes beginning install..

The podium/carpark is due for completion beginning of December, which will also allow the release of the town houses at GF.

• COMPLETION DUE Q4 2018 •

Next panel

Next panel

Next panel

• ADELPHI WHARF PHASE 1 •

• LATEST UPDATE •

DECEMBER 2018


Block A  

Due for completion – Late September

  • Lower Ground – Rooms 70% completed, final plumbing works underway.
  • Ground Floor – Rooms 95% completed, currently de-snagging
  • Levels 3 to 5 – Rooms 95% completed, currently de-snagging
  • Level 6 - Rooms 80% completed, snagging underway
  • Level 7 - Rooms 80% completed, snagging underway
  • Level 8 – Rooms 70% completed, final plumbing works underway
  • Level 9 – Rooms 70% completed, final plumbing works underway


Block B 

Due for completion – Late September 

Lower Ground – Rooms 70% completed, final plumbing works underway.

Ground Floor – Rooms 95% completed, currently de-snagging

Levels 3 to 5 – Rooms 95% completed, currently de-snagging

Level 6 - Rooms 80% completed, snagging underway

Level 7 - Rooms 80% completed, snagging underway

Level 8 – Rooms 70% completed, final plumbing works underway

Block C 

Due for completion – Late August 

  • Townhouses – Rooms 60% completed, final electrical works underway
  • Lower Ground – Rooms 97% completed, flooring to be laid
  • Ground Floor – Rooms 97% completed, flooring to be laid
  • Levels 3 to 4 - Rooms 97% completed, flooring to be laid
  • Level 5 – Rooms 80% completed, snagging underway
  • Level 6 – Rooms 70% completed, final plumbing works underway


Cladding to block C – 100% completed

Brickwork to block A & B 95% completed

Groundworks complete to the perimeter of block C allowing hardlanscaping to begin

Next panel

Next panel

Next panel

• ADELPHI WHARF PHASE 2 •

• LATEST UPDATE •

NOVEMBER 2018.

Next panel

Next panel

Next panel

• ADELPHI WHARF PHASE 3 •

• LATEST UPDATE •

NOVEMBER 2018. 

Building foundations have commenced followed by the main concrete frame for the blocks.

• DUE FOR COMPLETION 2019 •

Next panel

Next panel

Next panel

• GREEN QUARTER 7 •

• LATEST UPDATE •

DECEMBER 2018. 

Basement levels and Structural concrete frame progressing well. Concrete frame has completed 5 basement levels and 11 of the 15 floors above ground. Concrete frame is expected to be ‘topped out’ Q4 18. 

Structural Insulated panelling system has commenced with all works complete to level 3, further works have continued intermittently up to Level 6. Mast climbers have not been installed on all elevations to facilitate the install of the SIPS panels and external windows and cladding.

First fix of the lower levels is due to commence September 2018.  

Works are due for completion 3Q 19.

.

• DUE FOR COMPLETION 2019 •

Next panel

Next panel

Next panel

• FORTIS QUAY •

• LATEST UPDATE •

DECEMBER 2018. 

Next panel

Next panel

Next panel

• SILKHOUSE COURT •

• LATEST UPDATE •

OCTOBER 2018.

Floors 14 down to 3 - Practical completion end of December 2018 

Floors 3 down to ground - Practical completion end of March 2019 

Windows have been installed to the tower of the building from floors 15 down to 3. Scaffold is fully erect around the lower floors to allow the installation to continue. 

Units on levels 14- 10 are 95% complete, Electricians and Plumbers are now working their way down the building testing and commissioning which will allow the builders final snag to commence. 

Units on levels 9 – 5 are 85% complete, Flooring contractors are working their way through the building closing out flats which will allow the Electricians and Plumbers to start testing and commissioning 

Units on levels 4 - 3 are 80% complete, Decorators are now applying the final coat of decoration. Floorers will be following behind starting to lay floors 

Units on levels 2 – 1 and Ground are 35% complete. All 2nd side boarding is now complete allowing plasterers to start working their way through the apartments 

The cladding is 50% done with rails and pull tests been installed. All required mastclimbers and scaffold is now fully erect which will allow the cladding contractors to start working their way down the building installing the cladding panels.

• UNDER CONSTRUCTION •

Next panel

Next panel

Next panel

• BRIDGEWATER WHARF •

• LATEST UPDATE •

DECEMBER 2018.

Construction is now under way.

• UNDER CONSTRUCTION •

Next panel

Next panel

Next panel

• HALE ADDRESS •

• email •

• ALTRINCHAM ADDRESS •




BANK HOUSE

OLD MARKET PLACE

ALTRINCHAM

WA14 4PA


INFO@FORTISDEVELOPMENTS.COM

FORTIS GROUP

SUITE 4

RICHMOND HOUSE

HEATH ROAD

HALE

WA14 2XP

+44(0)161 974 5860